updating hammock task in MSP 2007
Forum TopicDear planners,I am using MSP 2007.Hammock activity is not updating itself.How to set auto update of hammock task.It is like update the tasks and hammock task will be updated.urgent helpRegards,kp
Dear planners,I am using MSP 2007.Hammock activity is not updating itself.How to set auto update of hammock task.It is like update the tasks and hammock task will be updated.urgent helpRegards,kp
Dear Friends Now Iam Working in a STP Project and Iam not famalier with the STP Projects..Every body can share their experience with me and it will be very useful for the scheduling.Can I get more details and functions of a Terminal Lifting station??...
Hi planners, Would any one tell me about changes in the project plan? I am working with a (civil) contracting company and doing a high rise commercial tower in Dubai. We also have a sister concern for MEP works. I am the only planning engineer in the...
Asta Power Project seems to be a powerful and flexible planning/project management package for controlling construction projects. Has anybody used it to manage process plant projects (Oil, Gas, LNG, Petro Chemicals, Power and Water etc) covering EPC/...
To my fellow planners in Australia, I’d like to ask a couple of questions, if I got approved from IEA as a professional engineer / civil engineer, will I be able to work in OZ as an Engineer? or do I need another qualifications / study?In order to w...
Hi,I need to do a program for work and I need to display schedule complete. It currently shows 0%, how do i change it to show relative to the start and completion dates i put in the programIm using p6v7Thank you in advance :)
I have been trying to import a project in P6. The project has budgeted man hours, but when i finish the import the hours are all changed. What is the correct way of doing it?
Morning all, I have a simple question: In your opinion, which software package best integrates scheduling, costs forecasting, payroll and purchasing? In effect a "Project Control" package instead of simply a scheduling tool. I'm currently using Prim ...
Since a couple of weeks all the project I open, when I add a constraint to start on or after date+ 0:00 after scheduling it uses the last previous time liek 08:00 or something. Calendar is set to 24/7 and I can start the activity at any given time (e...
Dear Friends It will be highly appreciated if you will be clearing my doubt ASAP. Eg .I have a task of block work of Quantity 400 M2 . Kindly clarify the production in the attached picture . 2.5 M2 per Hour means it is the production rate of one mas...
We have a standalone project where the tasks are currently linked FS and I would like to change the relationship to SS. The few tasks that would need to be FS I cna always change back afterward. Is there a method ?
Hello Fellow Asta Travellers, Would like to create two columns that show specifiic baseline periods from the same baseline - for instance baseline finish dates for year ending 2011 then another column showing 2011 to year ending 2012 out of the same ...
Hi Gents, I've used many project specified activity codes and recently our client had set up its own version of global activity codes with diff rent values, so they want us to clean up our activity coding system and use their coding. Is there any way...
Hi, can some one comment on how to display "Baseline % Complete" for activities as well as being summed up for the WBS levels as well. the project is currently 50% into progress and "scheduled % complete" values are not the same as the ones that i ...
Dear planners,I have a strange situation.i am using ms project 2007.the problem is milestone tasks not displaying 0d and % complete.this is happening for few activites only.when i add new activities they are showing the 0d and %complete.Any helpurgen...
Dear planners,this is kp.In MS project 2007 can we create layouts like primavera.Regards,kp
Afternoon I'm new to the forum and new to the planning game in general. I've been on the P102 Course - so I know the basics on using P6. I know how to set up projects and about relationships etc. Trouble is, I've got to know about baselining an...
Hi all, I've recently begun to research the idea of moving our mysql databases to a cloud environment (particularly a sql cloud environment, like this one). So I've had some questions pointed at me, and I still am not sure what to make of this sort o...
Dear all,Can we show text in a box in header filed in print layout in msp 2007.urgent help pleaseThankskp
HELP! I have a large project plan that is not working correctly. For example, in one WBS, I have Design Build Deliver Implement This all works fine as long as none of the tasks are set as complete. Once I mark a task as complete - for example Design...