Hi,
I need to do a program for work and I need to display schedule complete. It currently shows 0%, how do i change it to show relative to the start and completion dates i put in the program
Im using p6v7
Thank you in advance :)
Hi,
I need to do a program for work and I need to display schedule complete. It currently shows 0%, how do i change it to show relative to the start and completion dates i put in the program
Im using p6v7
Thank you in advance :)
ryan,
assign budget unit=1 and price per unit=1.
assign & maintain baseline,
start to update with actual dates.
Ryan,
Just load any resource to all activity with budget unit=1 and price per unit=1.
Hope it helps.
Regards,
figured it out ;)
figured it out ;)