I need to do a program for work and I need to display schedule complete. It currently shows 0%, how do i change it to show relative to the start and completion dates i put in the program

Im using p6v7

Thank you in advance :)

M
mukunda y 👤 Member for 17 years 6 months

ryan, 

assign budget unit=1 and price per unit=1.

assign & maintain baseline,

start to update with actual dates.

R
Raymund de Laza 👤 Member for 16 years 6 months

Ryan,

Just load any resource to all activity with budget unit=1 and price per unit=1.

 

Hope it helps.

 

Regards,