Spider Project Team
Corporate Partner...
...
A Delay Reason can be because of:. 1-Activity: driving predecessor, logic link . 2-Resource availability . 3-Calendar Exception: exception taking over any other reason, say an activity cannot work on month 3 but it is scheduled for month 1 b...
Project ControlSchedulingCost Control
Dear All, Never have this kinda experience, when I did a report loading some of units tabulation are less from the budgeted labor units. I’ve checked General, Status and Resource tabs. There are totally same like others but the tabulation is less f...
HiCan any one tell me the arabic translation of "Forensic Claims Analyst"Cheers
Dear all,im new in primavera P6 .When i update the progress of the project, the p6 calculates the progress of the activities but does'nt calculate the total % progress complete or WBS % progress complete . can someone help me?thank
Hi All, In Becoming an Expert Witness, what is the best protocol in how to manage your evidence , and Data, and how to organise your Report Writing. Kind Regards Stephen
Dear all,I seem not to be able to make the feature “Allow Performance Interruptions of no longer then” to work.In my test schedule Activity 1 has a calendar with exception on 25 Jan, which with weekend brings interruption of 64 hours., but I just can...
Hi,does anyone know if there is any industry standard rate for project controls as part of the overall project value. I know that it can be different due to the nature of the project, scope of project controls, etc and it must be around 3-5% of overa...
Dear ALL,Whenever i tried to create a Schedule Check Report, this dialogue box poped out and the report is terminated prematurally. because i am using a chinese version operating system, so some of the charactors are in Chinese. However, i guess som...
Dera all, I am not an expert in delay analysis .I just have a basic doubt reagarding my project .it have 4 phases & Critical Phase is phase 4.Now Phase 4 is delayed from client side & is still delaying from client side .Other 3 phases having float ....
Hi Guys, Here's an article showing how to identifying activities that do not exist in the Primavera P6 project baseline http://ow.ly/gTkZf Emily
Hi there. My question is, is there a way to keep my units/time from changing in my resources when i change my original duration. It is frustrating me because i cant figure it out, and am manually having to go back and re adjust my units/time. I thoug...