Delay Analysis

Member for

19 years 10 months

Hi Gary

Glad you picked this one up before me.

Hi Sankar

Whatever the cause of the delay the Contractor has the duty to mitigate the effect on the completion date(s) so squandering available float is not an option.

Best regards

Mike Testro

Member for

16 years 7 months

In response to your question:

1) To some extent, it depends on your contract -If you are applying for EOT in terms of relief from LADs, then it will depend on wether the LADs are applied in part to the completion of each of your phases, or to completion of the project as a whole. If you are applying for additional delay costs, these may have to be a proprotion of your overall prelims associated with phase 4, rather than the entire project.

2) Your say "project delay is mainly due to phase 4 delay." If some of the delay is not client delay, things get a lot more complex, and it will depend on the specifics of the delay -e.g. is it concurrent delay?

3) You need to check your contract, as the float on phases 1 2 & 3 may belong to the contractor, the client, or the project

4) Depending on all of the above, you may be able to use up your float on the other 3 phases without impacting on your EOT claim for phase 4. This is often called "pacing". If you are going to do this, make sure you have informed the client of your intention, and the justification behind what you are doing.

 

I am not an expert in delay analysis either. I am sure others with more experience in these matters will also respond.

Member for

16 years 7 months

Sankar,

 

Please only click on the "Save" button ONCE when posting a message. If you click it 13 times, you make 13 posts.

 

I'm now going to delete the other 12 posts.

 

Thanks,

 

Gary.