Identifying Activities That Do Not Exist In The Primavera P6 Project Baseline

Hi Guys,



Here's an article showing how to identifying activities that do not exist in the Primavera P6 project baseline http://ow.ly/gTkZf



Emily

M
Mike Testro 👤 Member for 20 years 5 months

Hi Emily

Quite a convoluted exercise.

Just copy and paste the task names & UID to columns in a spreadsheet and compare the two lists.

If it was a Lotus 123 spread sheet then the baseline duplicates can be stripped out of the other database on a few clicks.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts