Primavera P6 schedule % complete not calculated

Dear all,

im new in primavera P6 .

When i update the progress of the project,  the p6  calculates the progress of the activities but does'nt calculate  the total  % progress complete or WBS  % progress complete .  can someone help me?

thank

O
omid khan 👤 Member for 13 years

for activities. schedule % complete is calculated using the following formula:

Schedule % Complete(Act) = ( [Data Date] – [Baseline Start] ) / ( [Baseline Finish] – [Baseline Start] )

as you see the above formula is not related to the cost of the activity but
for wbs elements schedule % complete is calculated using the following formula

schedule % complete = pv/bac

as you see the above formula is related to the cost of the wbs element

so if the cost of a wbs element is 0 u get 0 for schedule % complete

if u want to have a good grasp of the issue read the following link:

http://www.plannertuts.com/primavera-p6-tutorials/primavera-p6-schedule-percent-complete-guide-1-1180/

A
antonio orsini 👤 Member for 13 years 4 months

Thank Alexandre.

i didnt use Duration % complete field. now is ok. But why rhe Schedule % complete is 0??

thank

 

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Hi Antonio,

open the View, Group and Sort dialog box

check the Show Group Totals option

also make sure you are using the Duration % complete field and not the Activity % complete

Alexandre

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts