Absence of proper Longest Path in a Schedule with many milestones
Forum TopicWe are making a schedule for a building with many contractual milestones which are given constraint "finish on" in P6. These milestones are linked with each other with FS relationship and lag 0. However, with this arrangement the schedule is not show...