difrence between orignal duration & at completion duration

R
rizwan khan 👤 Member for 13 years 9 months

Dear all

 I had problem with the duration which i was working , there is 

 

 

 

what is diffrence between orignal and at copletion duration , how we can use it  in primevera 

thanks you all

A
Arnold Puy 👤 Member for 19 years 1 month

Hi Rizwan,

The Original duration is the number of working days required to complete each activity based on the current schedule. However, At completion duration is the sum of the actual duration and the remaining duration.

Cheers,

Arnold

R
rajesh kumar 👤 Member for 13 years

hi

Orginal Duration -planned duration 

at cmpt duration nothing but  actua work performed during project

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts