Absence of proper Longest Path in a Schedule with many milestones

We are making a schedule for a building with many contractual milestones which are given constraint "finish on" in P6. These milestones are linked with each other with FS relationship and lag 0. However, with this arrangement the schedule is not showing a proper longest path. Is there any remedy for the same.

S
SANTOSH KUMAR PRASAD 👤 Member for 15 years 9 months

Hello Gulshan

Firstly check schedule Open ends, if there work on it with proper logic.
After that link your milestone
A) start Milestone : link with group latest start successor activity with SS 0 lag relationship.
B) Finish Milestone : link with group last finish successor activity with FF 0 lag relationship.

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts