Search

P6 - Event Codes

Forum Topic

Hello, Is there a place to see all the different event codes in P6 and what they mean? We have moved onto a cloud based server and seem to be getting a lot more errors than previously.  ThanksEmma

Oct 24, 2019

Curved Data Date - why? what? when? is it for?

Forum Topic

I am used to seeing a straight data date line. Lately I been seeing curves data date lines, ie curved out around certain activities.  I assume this is from a setting, and after googling it with-out getting an easy answer I am asking you.  What does i...

Oct 25, 2019

Modelling men and material logistics

Forum Topic

Hi all, Working on a concentrator build, greenfields next to brownfileds environment. Need to model the men and material flow to optimise bottlenecks, security turnstiles, change houses etc. as well as the way the laydown yard is set-out with require...

Oct 31, 2019

Cannot import XER file, "contains resource data"

Forum Topic

Hello Pplanners,I recently tried to import a XER file into P6 15.2, and I received the following warning/error message "This file contains resource data, import canceled"Does anybody know the reason of this message, that I saw for the first time?Than...

Oct 31, 2019

When to rebaseline a schedule

Forum Topic

Hi. I would like to know when is the best time to rebaseline a schedule. Is there a standard variance value that should be considered or is it different with each schedule? If it is different for each schedule what is the best approach to deciding th...

Nov 5, 2019

Problems with installing P6 EPPM 18.0

Forum Topic

Hi all.I got problems with. I've been installed1)Java JDK -OK2)Weblogik - Ok3)Oracle XE - OkBt when i'm installing EPPM Primaveraб Data base is'nt greating.I open a log and read such a problem: ORA-65096: invalid common user or role name  Has anyone ...

Nov 7, 2019

Beginner Resource Leveling Issue

Forum Topic

Hi, I'm fairly new to MS Project and have been doing some practice pieces before I look at using it for anything at work. To this end I've created a schedule for a large dinner I'm making over the course of a week - over 100 components so it is also ...

Nov 7, 2019

Primavera 18 opens last opened project upon startup!?

Forum Topic

Primavera 18 opens last opened project upon startup!?  How do I turn this off?  I think I read that it can be turned off in user preferences but that is not correct.  With last file I imported, something went bad.  And now primavera tries to open it ...

Nov 10, 2019

Resource % Usage in P6

Forum Topic

How do I go about in assingning resources with a specific % usage within P6? Looking to mirrior the same function as in Microsoft projects resources. Anythings helps. Thanks. 

Nov 14, 2019

P6 Not Exporting Full Cost Account ID

Forum Topic

I am trying to export the entire cost account ID into excel. It appears as if primavera only takes the end value of the ID. So if I have a cost acount ID 00A.01 it will only export 01. Is there any way around this? 

Nov 14, 2019

Date Difference between MSP and P6

Forum Topic

I have an activity for 22.5 days in P6 and MSP.   Both have calendars that are 6X10 with Sunday non working.   In P6 I get the dates 3/27/20 to 4/16/20 and in MSP 3/27/2020 to 4/24/2020.  There is a need to use the MSP plan as an overall roadmap and ...

Nov 15, 2019

Activity usage profile

Forum Topic

Does anyone know why actual bar in the activity usage profile shows a different number from what we get in the activity table column? We have set financial periods. Our “actual this period” doesn’t match with the profile.

Nov 17, 2019

SPI calculation in P6

Forum Topic

In our previous month’s update we had a forecast (remaining early)of 10 million for this month. This month our actual is much less than last month and is around 5 million. We have assigned previous month’s update as our baseline for this month. So th...

Nov 17, 2019

Weekly schedule % complete.

Forum Topic

Hi all,Just wondering, in P6 if there is any way to get weekly planned schedule % complete in excel. Thanks,Kind Regards,Syed

Nov 18, 2019

Overall Weightage by Cost

Forum Topic

Hello Everyone,Need Help.I saw a schedule in which the Progress is weighed by Cost.Each activity under each WBS has a cost. So everytime it is updated the WBS shows the % Planned and % Actual.Overall it shows % Completed based on Cost.So how can it b...

Nov 18, 2019

BI Export - working days and elapsed duration

Forum Topic

Hi In my model I extract tasks data according to line below from model file:<Column name="DurationDays" datatype="Duration" group="Date" formula="Duration / '1d'"/> The problem is that some tasks have duration in working days and some of them in elap...

Nov 18, 2019

Same plan 2 computers different calculations - help please

Forum Topic

Good afternoon/Morning depending where you are.A fellow planner has come to me with an issue today, he's finding odd calculations in his plan.  I've opened the same plan (we're in the same server).On mine the original duration is different, the remai...

Nov 19, 2019

Earned Value Tracker template

Forum Topic

Hello, I work in the Oil & Gas Engineering projects. The client has requested for a EVM tracker. Can someone share a template and brief guideline, on how to calculate it. Thanks for your efforts and time,Nisha

Nov 19, 2019