Weekly schedule % complete.

N
nadeem syed 👤 Member for 18 years 5 months

Hi all,

Just wondering, in P6 if there is any way to get weekly planned schedule % complete in excel.

 

Thanks,

Kind Regards,

Syed

Z
Zoltan Palffy 👤 Member for 16 years 10 months

your scheduled % complete is  from your basline schedule it is the total planned mahours for the project divided by the cumulatived manhours up to that month

i.e. total planned manhours 100 

total cumulative manhours at the end of that month = 10 

therefore 100/10= planned 10% complete

N
nadeem syed 👤 Member for 18 years 5 months

Hi, I have manhours assigned to each activity, what I'm trying to get in spreadsheet is literally Schedule % Complete, not budgeted units or remaining units or BL budgeted units.

Z
Zoltan Palffy 👤 Member for 16 years 10 months

planned of what ?

what is your measuring stick 

assign manhours to each activity then you will know the answer

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts