Hi all,
Just wondering, in P6 if there is any way to get weekly planned schedule % complete in excel.
Thanks,
Kind Regards,
Syed
Hi all,
Just wondering, in P6 if there is any way to get weekly planned schedule % complete in excel.
Thanks,
Kind Regards,
Syed
your scheduled % complete is from your basline schedule it is the total planned mahours for the project divided by the cumulatived manhours up to that month
i.e. total planned manhours 100
total cumulative manhours at the end of that month = 10
therefore 100/10= planned 10% complete
Hi, I have manhours assigned to each activity, what I'm trying to get in spreadsheet is literally Schedule % Complete, not budgeted units or remaining units or BL budgeted units.
planned of what ?
what is your measuring stick
assign manhours to each activity then you will know the answer