Hello Everyone,
Need Help.
I saw a schedule in which the Progress is weighed by Cost.
Each activity under each WBS has a cost. So everytime it is updated the WBS shows the % Planned and % Actual.
Overall it shows % Completed based on Cost.
So how can it be set up ?
Regards
Jithin
yes it will roll up
Thanks Zoltan,
So by this each WBS would have its own weightage and overall WBS would show the total progress Planned and Actual ?
Regards
Jithin
1st go to the PROJECTS directory
make sure that your project is open
click on the reources tab and at the bottom make sure that resources can be assigned to teh same activity more than once is NOT checked
go to activites now go to Resources and on the rigth select add
create an new resource call it lumpsum make sure that calculate cost from units is NOT checked
filter for all of the activites thet you want cost on
select all activities
right click
assign resource select LUMP sum
select file export and export the resource and cost to excel
populate cost values in excel for each actviity
save file
import back into p6
view show on bottom resource useage profile
done