SPI calculation in P6

S
SepSep Hoss 👤 Member for 14 years 2 months

In our previous month’s update we had a forecast (remaining early)of 10 million for this month. This month our actual is much less than last month and is around 5 million. We have assigned previous month’s update as our baseline for this month. So that 10 million forecast is now our baseline. But still our SPI is 1 in P6! So even though our progress is half of our baseline our SPI is still high.
Any idea what is causing this?

S
SepSep Hoss 👤 Member for 14 years 2 months

We only show revenue in our project. Baseline for earned value is previous month’s update which in our current month we have slipped a lot but SPI is 1!!

D
David Kelly 👤 Member for 21 years 7 months

Your talk of "actual" is confusing, SPI is a measure of Earned, not Actual. No change to Actual Hours changes SPI.

Which baseline are you using to calculate Earned Value in the Project's "Settings"

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts