In our previous month’s update we had a forecast (remaining early)of 10 million for this month. This month our actual is much less than last month and is around 5 million. We have assigned previous month’s update as our baseline for this month. So that 10 million forecast is now our baseline. But still our SPI is 1 in P6! So even though our progress is half of our baseline our SPI is still high.
Any idea what is causing this?
SPI calculation in P6
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
We only show revenue in our project. Baseline for earned value is previous month’s update which in our current month we have slipped a lot but SPI is 1!!
Your talk of "actual" is confusing, SPI is a measure of Earned, not Actual. No change to Actual Hours changes SPI.
Which baseline are you using to calculate Earned Value in the Project's "Settings"