Resource % Usage in P6

How do I go about in assingning resources with a specific % usage within P6? Looking to mirrior the same function as in Microsoft projects resources. Anythings helps. Thanks. 

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Eric, Sterling, Zoltan,

my mistake! I should have thought a little bit more before posting my answer

Alexandre

Z
Zoltan Palffy 👤 Member for 16 years 10 months

create a resource and if you are assign it as 8 hours per day it will automatically multiply 8 times your duration so

5 days = 8*5 = 40 hours this is the default basically 1 man per task

export the resource and units (manhours) to excel and make your modifications there and then import back into p6.

S
Sterling Gallagher 👤 Member for 6 years 8 months

Hi Eric

The setting is in - User Preferences - Dates -  Units/Time format  - Change to (show as a percentage (50%)).

Then in the Activities screen when you go to the resources tab of the Details window, add the column "Remaining Units/Time".  This column will be shown as a % of the resource calendar assigned to the resource you add to the activity.

If you leave the Units/Time Format as "Show as units/duration (4h/d)", the Remaining Units/Time column will be represented as hours of the assigned resource calendar.  Just be aware when you have the setting in this configuration, the "Durations Format" of the "User Preferences - Time Units" tab will affect how the "Remaining Units/Time" is represented.  For example if you set the "Durations Format" to hour, the "Remaining Units/Time" will say 1/h wich is equivalent to 8h/d or 100% if the resource calendar is your standard 8 hour per day calendar.

If you set the "Durations Format" to "Day" the "Remaining Units/Time" will say 8/d wich is equivalent to 1/h or 100% if the resource calendar is your standard 8 hour per day calendar.

 

Hope this helps

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Hi Eric,

assigning resources with a specific % does not exist in P6; the workaround is to assign a specific value in the Remaining Units per Time field; for instance, key in 4 (for 4 hours/day) instead of 50% (50% of 8h/d)

Alexandre

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts