activity name
Forum Topichi, guys,how to remove activity name showing in gantt chart view. i tried bar settings and its not working
hi, guys,how to remove activity name showing in gantt chart view. i tried bar settings and its not working
Please need assistance in filtering baseline against my recent changes or vise versa:If I want to filter out which activities has been recently changed or date moved against my latest BL just for double checking, which parameter/s I should use in my ...
I am re-baselining a project and coming upo against no end of issues with it. Only some activities in the baseline need to be changed hence why I am updating and not creating a new baseline. BUT P6 seems to lose a lot of the activities after the base...
Hi,Is it possible to lock a layout/settings to one project so that everytime that project opens the layout opens? The reason being I have 2 projects one is a target and one is a Project program. If I were able to lock the colors of the WBS then peopl...
Hi I am using Pimavea P6 Release 8.2 I would like to know how to change the calendar used at the Group Totals. (Summarised to Project Level) Initially it uses Project Default Calendar as shown in the Calenda.....But on changing the default calendar ...
While attaching documents to an activity or WBS, Maximum how much of GB file I can attach?
PRM DBAccess Error: Database Server Error: ORA-12952: The request exceeds the maximum allowed database size of 4 GB ORA-06512: at "ADMPRM$PM.RT_UDFVALUE_DEL", line 3 ORA-04088: error during execution of trigger 'ADMPRM$PM.RT_UDFVALUE_DEL'
http://3d-wbs.blogspot.fr/2013/09/part-91-cost-accounts-tree-structure.html BR, Jean-Yves Moine.
Hi all I've been asked to put amounts of money against various activities so the QSs can do earned Value Analysis. At first I just used a user defined column and dropped them in like that, but the commercial manager wants me to put them in properly ...
Here's some great Fill Down examples complete with screen grabs in Primavera P6 Professional http://ow.ly/oVdAn
Hi All, I've a curiousity for you and I hope you can answer for me. I'm cleaning up an old database and reducing the number of global calendars to what is practical/needed. When a calendar cannot be deleted because it is assigned but the Utilizatio...
HiI've allocated cost accounts to the resource allocation on an activity but, when organising in the activity layout to report on EV per cost account, it groups by 'mech labour' and mech labour,' with a comma.It does this for some of the costs accou...
Dear guys,I am using P6 r8.2 and i am having some difficulties regarding the bar neck. In the working window, you can see the neck (out of sequence) but once i switch it to print preview, the neck was not there anymore, it is just simply a straight ...
Hi hope someone can advise - I am new to P6 ( from MS project environment) and cannot get a %compete figure to roll up into the wbs top level in the activity view (as you can in project).I have tried it in the WBS layout but is not he same pictorial...
Dear colleagues,I imported a project plan into MS Project 2007 from Primavera P6. For the first 12 activities, the start and finish dates were the same. But starting from the 13th activity onward, I've noticed that the start and finish dates in pro...
Hi there folks, This is my first ever post so go easy on me. I am relatively new to Planning and to Primavera (as far as experience goes, 2 years in the planning world is not long at all and I have a lot to learn) however I am very keen to learn as ...
Dear All,Please anyone could inform me how to update project schedule through time sheet in p6 specially, how prepare and put the project time sheet in p6 database to start update ?
Hello Planners,One customer of mine is having hard time with his Tilos project: one of the project summary tasks is no longer visible and clickable in the Time Distance View, although it displays normally in the Gantt Chart and the subproject Tasks L...
Hello,I need to allocate a lump sum cost to some tasks of the project, and have 100 percent of the cost showing at the very beginning of the task. Can anybody help?Alexandre
Hi Guys,I have to workout a schedule for construction of Coal Handling & Preparation Plant (CHPP) but i have no idea of level three construction activities & their logical relations. Can anybody help me in this regard?Thanks in advance.