commas in cost accounts

Hi

I've allocated cost accounts to the resource allocation on an activity but, when organising in the activity layout to report on EV per cost account, it groups by 'mech labour' and mech labour,'  with a comma.

It does this for some of the costs accounts but not all. when I check the cost accounts on the activities, they are the same cost account. If I group by cost account in the resource assignment tab, it groups them under one i.e. 'mech labour'. But I can't report on EV in this layout.

is there any reason why a comma separates activities which have the same cost account allocated?

Thanks

 

 

L
Lesley Pickering 👤 Member for 22 years 8 months

Hi Shimmo

Sorry about the delay in replying.

I have multiple resources allocated on some of the activities but not on others. However, some cost accounts with the comma have multiple resources assigned and some without the comma have mulitple resources assigned. So that doesn't seem to be the driver for the comma.

Cheers

Lesley  

J
James Shimmon 👤 Member for 13 years 3 months

Hi,

Do you have multiple resources assigned to the same activity and if you do, are they all assigned to the same cost account?

Cheers

 

Shimmo

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts