Dear All,
Please anyone could inform me how to update project schedule through time sheet in p6 specially, how prepare and put the project time sheet in p6 database to start update ?
Dear All,
Please anyone could inform me how to update project schedule through time sheet in p6 specially, how prepare and put the project time sheet in p6 database to start update ?
How the primary resource reflect time sheet is this in primavera file and if in excel or any other format how to prepare to match with primavera to arrive for admin (P.M) to approve
Hi Amro,
First you have assisgn activites to a primary resource and then that resource will be able to see his assigment in time sheet module. once allocated, resource can log actual units in time sheet module and will submitt you for approval. You will have notifcation for approval. After your approval these actual units will incorporate in Master Plan.
Brgds, Imran