Hi All,
I've a curiousity for you and I hope you can answer for me. I'm cleaning up an old database and reducing the number of global calendars to what is practical/needed. When a calendar cannot be deleted because it is assigned but the Utilization comes up empty for Projects and Resources, why is that?
All help appreciated.
Regards, Kylee.
Hi All,
The answer is apparently that the calendars are assigned to baselines that are not found/ shown in the utilisation. To find these I need to use scripts.
Regards, Kylee.
the Utilization comes up empty for Projects and Resources, why is that?
Can u explain clearly this part....