100% of the cost at the beginning of the task

Hello,

I need to allocate a lump sum cost to some tasks of the project, and have 100 percent of the cost showing at the very beginning of the task. Can anybody help?

Alexandre

T
Thorsten Balthasar 👤 Member for 14 years 11 months

Alexandre,

 

by default TILOS spreads the cost allocation on the duration of the task.

For your need you may

- create a milestone for each of the corresponding tasks

- assign Start-Start-Links to locate the Milesones at the beginning of the task

- assign the cost to the milestone

- you may also switch off the display of those milestones with layers or filter

 

regards

Thorsten