The Most Important Question for Troubled Projects
Forum TopicHi Guys,Here's an article on The Most Important Question for Troubled Projects http://bit.ly/t1NeVfI hope you find it useful,Emily
Hi Guys,Here's an article on The Most Important Question for Troubled Projects http://bit.ly/t1NeVfI hope you find it useful,Emily
Dear All, Is it possible to deactivate temporarily a relationship in Primavera P6 ? let explain : I have 3 projects P1, P2 and P3. The activities of P1 and P2 are the predecessors of P3. I'd like to know the impact of P1 alone to compare it with the ...
Hi In Primavera PM 6.7 with Progress Reporter is it possible to edit or unapprove a submitted and approved timesheet? The timewriter can edit them up until they're submitted (and optionally rejected) The time approver can edit the timewriters timeshe...
Hello everyone, I am working in civil projects and my Project Manager is always telling me that "Why Overall Programme Progress % and BQ % progress(calculated by QS) does not match. Anyone advise or solution to this scenario to link the BQ claim an...
Hello guys, I am currently working on a petrochemical project, and my previous orientation is from High Rise Civil Construction Planning, I was a Commissioning Engineer before in a power plant but I think that will not help me much to plan for a proj...
Dear All , Can I show the late baseline bar on the layout? Thanks and Regards,
Friends Please help me to utilize the finish finish relation.. Excavation is SS with Dewatering the same day...Dewatering is FF with Back filling Manhole Installation Back filling I have make relations for Dewatering Dewatering SS Excavation is pre...
Hey everyone i have been searching for this and think the answer is no but just wanted to clarify..Is there anyway to set a constraint on hours spent on an activity or do constraints only apply to dates?Sorry if its a stupid question im quite new to...
Learn Primavera/ MS Project from a highly experienced PM Professional ( 37+ years)Contact: [email protected]
Hello fellow planners,I recently tried to import a 400 activity schedule from MS Project 2003 into Primavera PM6, via either a MPP or XML file.Almost everything went right, except the WBS which looks really strange: only the project level and the 1st...
hi everyone ! a colleague of mine, working with P6 v6.2.1 had a strange problem :he had, on every task of his project, an original duration and a resource (labor).budgeted units calculated just fine, but when he went to replace the resource with anot...
Dear gys,I have a problem in P3 version:I have a project that its activity duration type is hour, can I change the type to day and also I don't want to break the decimal part of duration beacause the date will change. how can change it?Can I change t...
Hi....I have a standalone P6 installation (Windows-XP) and it was running ok until this morning. Our IT person did something today with it and now I am getting the "configure database message" when i type in my user name and pw which was admin/admin....
Hi....I have a standalone P6 installation (Windows-XP) and it was running ok until this morning. Our IT person did something today with it and now I am getting the "configure database message" when i type in my user name and pw which was admin/admin....
Hi AllI'm using Level of Effort activities in P6 and want to know the settings for the automatic update of the % completed of the LoE. It does not work in my schedule. Could everyone give me a hint how to solve my problem??? Thanks Frank
What benefits the Owner can gain by awarding EPC or Design & Build Contract to a Contractor. For eg: a. The Owner defines the Scope of work, Specification, Lumpsum Budget, Quality, Duration, Basic design etc. b. The Contractor has to develop the deta...
Good morning,Normaly ,baseline dates don't change when we update!?Thanks
I have noticed something weird with my P6 - I have a load of filters created but for some reason Primavera then creates duplicate filters suffixed with an _1, _2 etc - in some cases I have 6 filters the same with different numbers at the end. What is...
Hi.I just started here at Planning Planet and I need a big help. In my new job was asked me to develop a tasks for the co-workers at planning team. The planning work flow ideas for seniors and juniors planners. Ideas for report.I am a planner for ere...
Hi.I just started here at Planning Planet and I need a big help. In my new job was asked me to develop a tasks for the co-workers at planning team. The planning work flow ideas for seniors and juniors planners. Ideas for report.I am a planner for ere...