Why the baseline project start change when I do F9

Good morning,

Normaly ,baseline dates don't change when we update!?

Thanks

W
walid Lahiani 👤 Member for 15 years 7 months

Good morning,

I did right click,bars,i checked primary baseline,so I had the bar target graphic

thanks,

F
Forrest Chen 👤 Member for 14 years 5 months

right click on gant chart ----- choose 'Bars' ---- find the column named 'timescale' ----- change whatever is chosen into 'project baseline' (same row as project baseline)

cheers

W
walid Lahiani 👤 Member for 15 years 7 months

Yes,

In Project->Assign baseline->My choice was current project and now I changed it to Target which I did with Project->maintain baseline

 

Thank you

R
Raymund de Laza 👤 Member for 16 years 6 months

Walid,

You might have assigned the current project as your baseline.

Please investigate.....

 

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts