Friends
Please help me to utilize the finish finish relation..
Excavation is SS with Dewatering the same day...
Dewatering is FF with Back filling
Manhole Installation
Back filling
I have make relations for Dewatering
Dewatering SS Excavation is predecessor
Dewatering FF Back filling also predecessor
Is this relation is right ???
Regards
Arun
Arun,
There are many dewatering systems;
Mikes suggestion I believe on target as it can be adapted to many situations. The following screen illustrates the concept of using the hammock activity that in your software might be called something different, the approach can be similar. Note setup activity is of the ALAP type, use this type with caution, preferably limit such activity types to a single successor.
I added resource loading and use of shifts as to illustrate why sometimes a single activity is not enough. You will notice setup and removal are activities with fixed duration and working on a regular shift while dewatering is a 24/7 activity that requires work during 3 shifts. The dewatering activity might be delayed by pumps delivery and it will delay your excavation, also removal of dewatering can be delayed, need not to be continuous.
Best regards,
Rafael
Sorry Mike
Friends please help
Hi Arun
Your dewatering activity is best set up as a summary bar or hammock over the excavation - backfill tasks.
You will need to add some time for installing and removing the dewatering systems so it is not a true SS - FF relationship.
As a rule you should avoid all SS and FF links and work with FS only.
Best regards
Mike Testro