EPC & DB Contracts

K
Kannan CP 👤 Member for 17 years 11 months

What benefits the Owner can gain by awarding EPC or Design & Build Contract to a Contractor.

For eg:

a. The Owner defines the Scope of work, Specification, Lumpsum Budget, Quality, Duration, Basic design etc.

b. The Contractor has to develop the detail design, drawings, Procure the materials, construction works, hand over the work as per the Owner's requirement specified in the Contract agreement. Since it is Lumpsum payment, the risk of price hike come to Contractor's shoulder.

c. Which type Contract the Owner can select- EPC or DB?- In both type, all the responsibilty comes under a Main Contractor ( or joint venture with a leader), who has to perform the design, eng, procurement, construction and commissioning. Then what is the difference between these two types?

Regards

Kannan

M
Mike Testro 👤 Member for 20 years 5 months

Hi Kannan

There is no difference - just different names for same procurement route.

Engineer Procure Construct  is American -- Design and Build is British

The benefit for the employer is that the all the risk of the design - construct interface is with the contractor.

Unless that is the employer insists on checking the design - in which case a lot of the time risk comes back to the employer.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts