How can I show the late baseline bar on the layout?

Dear All ,

Can I show the late baseline bar on the layout?

Thanks and Regards,

D
David Kelly 👤 Member for 21 years 7 months

Copy the baseline you want the dates from (P6 v7 lets you do this in place)

Restore the baseline to the live EPS

Open the project you just restored

Run a global change to set :

Planned start = Late Start

Planned Finish = Late Finish

Demote the project to being a baseline again

Use that baseline - set it as secondary or tertiary - and as with ALL BASELINES it uses the planned dates to draw a bar.

F
Ferdinand U. 👤 Member for 18 years 10 months

you can try to create UDF for late bar using excel import/export copied from your baseline late dates

F
Ferdinand U. 👤 Member for 18 years 10 months

you can try to create UDF for late bar using excel import/export copied from your baseline late dates

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Ayman,

I am afraid there is no early and late baseline bars in P6 as there was in P3; as far as I know, P6 only manages early bars when you maintain and assign baselines

Alexandre

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts