Search

Custom variance column on P6

Forum Topic

Hi All, I want variance column to show opposite from default ,example baseline start date is 1 April but actual date is 2 April . The default variance , “ BL-start, “shows minus 1; I want to make a custom field to show the other way, +1 instead of mi...

Feb 21, 2025

MPX Import Error

Forum Topic

Hi,Im attempting to import an MSP file in to P6.I have exported as an xml (after checking for blank lines and summary tasks etc) but the file doesnt open in P6.I have converted the mpp to mpx and then tried to import - however, I get the following er...

Feb 21, 2025

Show Resource Critical Paths

Forum Topic

Hello,I have a schedule with a non-critical but resource-overallocated path through tasks A-B; and a critical path through task C, which is not resource-loaded. When I level the schedule, the path, including tasks A-B, becomes critical, and the path ...

Mar 5, 2025

Update WBS code and name in bulk

Forum Topic

Hi,I need to build a new schedule and its structure is very similar to one already established. I copied the WBS from the old project to the new one, but I will need to perform lots of modifications, notably on WBS codes and names.Is there a way to p...

Apr 9, 2025

Update Daily progress from excel into planning tool

Forum Topic

Dear ForumCould yo kindly help me please with my question that i am struggling much: There is task (actually lots of tasks, but for simplicity i will consider 1 task) that started at some time in the past and gradually was progressing on a daily basi...

Apr 14, 2025

Error Code PRMDB-0900-0

Forum Topic

Dear Planners, i'm using P6 version 24 Server , with 5 Users , every thing is ok, untill the user is leaving the P6 idle ( not used for 10 to 15 min, then when the user try to dop any filter or layout the below error showing up/   Event Code: Error C...

May 15, 2025

Global Change Parameters

Forum Topic

Hi, Can anyone help with what the Global Change Parameter 'Programme and Logic Changes' does? What kind of things can I change under this? Thanks in advance 

May 16, 2025

Baseline/Updated program of works

Forum Topic

Hi AllI have query that I have recieved Main Contractor Program of works as first program during the execution of project with Baseline dates and Updated/Revised dates together,Program of works also carrying -36 days TF,I am claiming this program wit...

May 20, 2025

P6 Prof v24.12 XERP330Convert.exe

Forum Topic

Hello,I want to know where in the P6 Professioanl v24.12 file structure to find the P6 XER to SDEF format conversion program, XERP330Convert.exe, so I can write an article to help direct others in converting XER files to SDEF format.So far, I have be...

May 21, 2025

P6 (non cloud version)

Forum Topic

Hello guys,I'm about to embark on a PhD in Project Management. I hear that P6 is available free for non-commercail activites.If so, I'm after the version that is installed on my laptop and NOT the cloud version as I travel a lot and work while flying...

Jun 17, 2025

Expected Finish Impact on Free Float

Forum Topic

Does anyone know why using “Expected Finish” constraint for in-progress activities turns these activities’ Free Float to zero, even when the successor activities are days or weeks away?

Aug 11, 2025

New Website

Forum Topic

Dear Friends, We’re currently beta testing our new community portal. Rather than delay access while we test and retest behind the scenes, we chose to go live and evolve in real time. We hope that was the right call—and we truly appreciate your patien...

Nov 4, 2025

Summary Schedule; L4 to L2

Forum Topic

Hello, I'd be grateful if anyone could give me some pointers as to how I might share my Level 4/5 working level detailed schedule with the client. I dont want them to see all of our secrets and also dont want to have to create a duplicate, but more s...

Nov 13, 2025

Is the delay excusable?

Forum Topic

Our contractor is building a office block. The structural steel was scheduled to arrive on site in the 12th week, but the nominated supplier delivered it two weeks late. The contractor missed the milestone for completing the steel frame, pushing back...

Nov 13, 2025

Construction Testing, Commissioning, Handover & Start-up

Forum Topic

Every wondered how to get more feedback from the project team on your schedule backend for those last 2 activities - Commissioning & Handover? You are at the very start of the project with very little commissioning and ops input so you just put those...

Dec 6, 2025

Terms of Service (ToS)

Page

Terms of Service (ToS) 1. Acceptance of Terms By accessing or using Planning Planet, you agree to comply with these Terms of Service. If you do not agree, please do not use the site. 2. Membership & Accounts • Members must provide accurate informatio...

Dec 11, 2020