Opinion or Assistance requested: Is there a different way to import & export to excel FILTERED pred / successor import data than to give the pred and successor a unique logic note code, then the matching activity a unique activity code. Otherwise the problem, or bug, or tricky issue is that ALL relationships are exported - relationships DO NOT follow the activity filter export. This makes is very difficult to import in activities with multiple users because the relationship import might over-right changes on other, non-filtered activities by others or say older select data into a later updated version. The problem is relationship data only applies a logic specific filter, and the only column that a variable can be applied is the relationship comment column. The xer and xlm exports do not have a filter option. Is there a 3rd party software or Macro than resolves this?
Difficult to export only select predecessor and success data - only exports them all
Forum Sponsor
Top Posters
christiandt
0 posts
J Vaartjes
3 posts
Aidar Kurmantayev
0 posts
Noe Radovan
8 posts
GeoVe
0 posts
James Williams
74 posts
Johannes Vandenberg
14 posts
Soheil Barekat
4 posts
Peter Holroyd
51 posts
Neil Atkinson
5 posts
You may join our free webinars and register ahead of the schedules - Webinar Schedule - Primavera P6 Add-On Tools and Safran Risk
You may join our free webinars and register ahead of the schedules - Webinar Schedule - Primavera P6 Add-On Tools and Safran Risk
here is a solution
1. copy the project
2. filter for what you do not need
3. You are left with what you want
4. Export to excel do what you want to do in excel
5. Export the data again from the project that has everthing then delete the data not the headrers
and paste the data from the filter file into the project files that has everything
6. import into p6