Hi,

Im attempting to import an MSP file in to P6.

I have exported as an xml (after checking for blank lines and summary tasks etc) but the file doesnt open in P6.

I have converted the mpp to mpx and then tried to import - however, I get the following error:

Image removed.

 

Im assuming the error is the ORA-01400 cannot insert null into.... but I really dont know where to look in MSP to find the issue.

Any assistance would be really appreciated.

Z
Zoltan Palffy 👤 Member for 16 years 11 months

there is only one program that I found that can do this correctly than that is 

xertransfer

https://www.xertransfer.com/

this is an addin utility ot MSp and you can convert to P6 from MSP or to MSP from P6

it even lets you map fields 

everyone program that I used did not convert correctly. 

Forum Sponsor

Top Posters

christiandt
0 posts
J Vaartjes
3 posts
Aidar Kurmantayev
0 posts
Noe Radovan
8 posts
GeoVe
0 posts
James Williams
74 posts
Johannes Vandenberg
14 posts
Soheil Barekat
4 posts
Peter Holroyd
51 posts
Neil Atkinson
5 posts