Search

Close an unfinished project in Primavera P6

Forum Topic

Hello, I am trying to close a pfoject in Primavera P6, which has not been completed but has to be closed untimely.Some activities, which had been planned earlied and which were going to start in the future, never started.How do I properly close it in...

Jul 25, 2017

Calendar - 7 Day Working Week

Forum Topic

I am creating a programme to completion that will require weekend working. I have set the calendar to 7 day working week but when I set an activity to work saturday and sunday, the activity bar jumps to the monday. How do I prevent this from happenin...

Jul 25, 2017

Convert Microsoft Project to WORKING .xer File

Forum Topic

Hello All,I am trying to import a microsoft project file to Primavera P6 version 7.0.I have done this in the following order:1. open project file using asta and then save as an xer file (it opens fine is Asta with all logic and WBS correct)2. import ...

Jul 25, 2017

Unable to copy P6 Schedule

Forum Topic

Hello,I have a schedule in P6 EPS that cannot be copied or make reflection. I can copy or make reflection of other schedules. I check all the settings of that particular schedule but they are the same as other schedules. Does anyone know why or exper...

Jul 29, 2017

DRAWING PRODUCTION MANAGEMENT

Forum Topic

Hello, Does anyone have a recommendation for a program to track the time spent on drawings against a budgeted $ or time amount? Can this be done with VW based on the drawing list created and be tracked by inputting the time spent into a spreadsheet i...

Jul 29, 2017

But For Baseline Delay Methodology

Forum Topic

I am analyzing a delay claim submitted by a contractor to an Owner. They are using a "But For Baseline" schedule as the basis to measure delay.The Baseline schedule included closeout activities (60 days) following construction completion to Final Acc...

Jul 29, 2017

P6 did no automatic re-calculate Date when update schedule

Forum Topic

Dear all,I'm newbie in group. I have a problem when update Schedule in Primavera as below. Hope get your clarification, instruction:* When i update activity in P6 by manual follow these steps:- Step 1: Create Baseline- Step 2: Update activity (Depend...

Jul 31, 2017

Assigning Updated Schedule (Has actuals) as Baseline

Forum Topic

Dears,I have a issue while assigning the current schedule as baseline which has actuals already.I have already changed the Planned Start=Start and Planned Finish=Finish.It works fine for Non started and Completed Activities.But for all in progress ac...

Jul 31, 2017

Assigning Updated Schedule (Has actuals) as Baseline

Forum Topic

Dears,I have a issue while assigning the current schedule as baseline which has actuals already.I have already changed the Planned Start=Start and Planned Finish=Finish.It works fine for Non started and Completed Activities.But for all in progress ac...

Jul 31, 2017

Import Relationships

Forum Topic

I want to import realtionships from a P6 file 1 (correct relationships) in to a different P6 file 2 (incorrect relationships).Doing it manually is possible but highly time consuming as I may have to touch 700+ activities.Importing relationship data f...

Aug 1, 2017

Asta changing date modified on .pp file automatically

Forum Topic

Hi all,I am using ASTA version 14 and I am trying to figure a way around something which might be very simple.When I open an old file say from a year ago to just have a look at and then close the file, the software seems to change the "Date Modified"...

Aug 2, 2017

relationship lag scheduling - detailed calculation algorithm

Forum Topic

Hi,Any suggestion on where to find a well-detailed explanation of how the lag between different activities in P6 are scheduled?I am experiencing some strange behaviors in particular cases, for which I am not able to provide a rational explanation.e.g...

May 1, 2018

132 kv substation turnkey project schedule

Forum Topic

I am involving in a planning of turnkey Substatiin construction in India.It is completely new field to me.Can any ine suggest with the sequence of activities which is normally used.If possible any sample schedule of it to get overall idea.

May 1, 2018

P6 SCHEDULE PROBLEM!!!

Forum Topic

Hi guys,I have a problem with my p6.I am done with my planning and I want to put my new data for the next month manually;*First problem=When I  click the start box in status bar and change the data with a different date finish box doesn't change auto...

May 2, 2018