Hello All,
I am trying to import a microsoft project file to Primavera P6 version 7.0.
I have done this in the following order:
1. open project file using asta and then save as an xer file (it opens fine is Asta with all logic and WBS correct)
2. import to P6 in the normal imort method for an xer file however the import loses some links and activities are no longer in their correct WBS. All the activities, links and WBS are present but the activities are no longer in the correct WBS, all are under one new WBS that the import seems to have created
How can I import to P6 without this happening?
thanks in advance
short answer is NEVER the conversions is never 100% There are many differences between the 2 programs let along introducing a 3 program asta.
Why noty import the microsoft project file into P6 why involve another software to interpurt it ?