Assigning Updated Schedule (Has actuals) as Baseline

Dears,

I have a issue while assigning the current schedule as baseline which has actuals already.

I have already changed the Planned Start=Start and Planned Finish=Finish.It works fine for Non started and Completed Activities.

But for all in progress activities i have an issue.Schedule % is not matching with the performance %. Could any one suggest solution on this regards please.

 

Not Activity % completion type is :Physical % Completion