Hello,
I have a schedule in P6 EPS that cannot be copied or make reflection. I can copy or make reflection of other schedules. I check all the settings of that particular schedule but they are the same as other schedules. Does anyone know why or experience it before?
My P6 version is 15.2.13.
Thank you.
shoul dbe same place where u saw superuser settings
I am an Admin Superuser. The problem is only for a specific project.
I have looked for the option of "Create Project within EPS" box but couldn't find it. Can you provide direction to that option?
Thank you
ot appears that you do not have the rights to do this. Go to Admin then Seciruty profiles and look at why type of user that you are sucj as end user, Project Magager, Super user. Look at the column where it says has Privilege. Look at this from the Global Profile was well as the Project Profile.
If you problem is only for this specific project then look at the project profile see if Create Project within EPS box is checked.