Primavera P6 Schedule Progression and Out-of-Sequence Activities

Here we look at procedures for handling out-of-sequence activity schedule progression using Primavera P6 http://ed.gr/cwdi

S
sharon Maxwell 👤 Member for 9 years 1 month

Out of Sequence Progress occurs from a deviation in the original planned logic that was set up in the baseline schedule. It can occur when work is executed in the field in a different order than was planned in the schedule. The result can affect your project’s logic, which dictates the order of execution of activities.

Click here for more details :- Oracle Training 

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts