Search

Ground improvement Production rates - Vibro piling

Forum Topic

Hi,Im trying to find out more information in respect to the output/production rates for vibro piling (stone column/ top feed process) has anyone have anyhistorical/empirical data? I have managed a project some time ago in which this method of ground ...

Jul 19, 2012

Mandatory Finish - Longest Path ?!?!?!

Forum Topic

hi.i have tried to do the following: creating a Finish Milestone (called FINISH) with a Mandatory Finish with its only Predecessor another Milestone (PROJECTED FINISH). the idea is that the FINISH activity would never fluctuate while the PROJECTED FI...

Jul 19, 2012

Civil Engineering

Forum Topic

Hi Everyone, I was just wondering if anyone would be able to explain some of the processes carried out in civil engineering.I come from an electrical background so I have no knowledge of civils or any activities they carry out.If i was to carry out t...

Jul 20, 2012

Original Duration change equal to Remaining Duration???

Forum Topic

  Need help please.... Why is it that Original Duration in the Summary Level will change equal to Remaining Durationafter I update some activities??? Due to this reason my Duration % Complete in the Highest or Project Level will always be 0% since Du...

Jul 20, 2012

Tracking Progress & CPI, SPI

Forum Topic

I am using MS PROject to track my project progress and to find the cost and variances for my project.under view->tables->tracking I am able to track my project. one of my project requirement said, "a task actually started 2 days late" my question is ...

Jul 20, 2012

Remaining units - Primavera

Forum Topic

Hi Looking for some help. In the schedule I am currently working on , I do not want to record actual units against each activity. Is there a way in Primavera to make the remaining labour units = estimate to complete labour units? This would mean as t...

Jul 21, 2012

Print Activity Codes

Forum Topic

Hi everyone, Im New to P6, my question is how to print the project activity codes. Thanks a lot.

Jul 23, 2012

Apartment Modifications Schedule

Forum Topic

I am currently working as Client rep on a residential tower of high end apartments. The Contractor is expected to allow the Client to introduce apartment modifications during the construction phase  in a random manner. ie: the Client can introduce ch...

Jul 23, 2012

Resource Loading using Import/Export

Forum Topic

Dear TeamI am having problems with Resource Loading using Import/Export. I am trying to Importi Resources and Roles, with Budget Labor Units and Budget Cost, but after the process, the entries for Resources and Roles are fine but the Budget Units are...

Jul 23, 2012

Status Update for New Activities Does Not Reflect in Summary Level

Forum Topic

Dear all,I'm currently using live programme(may add/remove activities follow site situation on monthly update basis) for status update with submission programme as baseline. However when doing statusing, the summary does not capture the performance %...

Jul 24, 2012

P6 R8 standalone- Old backup restore by mistake in SQL 2005

Forum Topic

Dear All   Please advice in the situation mentioned below. I am working on P6R8 standalone application on SQL 2005. By Mistake i restored an old data backup file in SQL 2005. My whole working files got lost , As they were not the part of old data bac...

Jul 24, 2012

Exporting Filtered project data

Forum Topic

Hello everyone, I want to export a project for only selected data. Is there a way I can do this? Thanks Ijaz

Jul 24, 2012

Restore Project P6

Forum Topic

Hi Everyone, Existing project is restored into another computer the resource loading normally changed. What is the procedure to make sure that the total project budget manhours and allocation of manhours for each activity will always be the same. Is ...

Jul 25, 2012

Listing Projects That Resources Are Allocated To

Forum Topic

Hi,Im trying to display which Projects each Resource is ultiised on, but cant work out how to do it.I know you can almost get there by opening each project but I'm trying to display it through the Resources Workspace. Anyone got any ideas?Cheers.

Jul 25, 2012

Problem with baseline incluing actual date

Forum Topic

Dear All, Plz help I've a baseline schedule with some actual dates and duatation % complete. but when i assigned the same to updated prgramme the BL start and BL finsh dates are not the same i assigned .............. Regards, Amir

Jul 26, 2012

P6 v7 -Unable to connect to database

Forum Topic

Dear All,Good day!I encountered this problem a few times. On other PC's when I installed P6 v7 stand alone, it won't start. After I input the password it does not start the program but gives a message "Unable to connect to database.". In one laptop I...

Jul 26, 2012

Stickies

Forum Topic

I note a couple of Stickies have been used on the Accreditation discussion board to ensure the Guild presentations are always highly visible.   Could we use the same methodology on other boards? I think it would be a great idea to have an FAQ sticky,...

Jul 26, 2012

Asta Task per line Mode

Forum Topic

I have recieved a programme which has used the Task per line mode to put multiple activites on a single line. Is there a way to put eeach actvity on its own line - apart from expanding the view!! I dont want works on multply lines

Jul 26, 2012