Dear All,
Plz help
I've a baseline schedule with some actual dates and duatation % complete. but when i assigned the same to updated prgramme the BL start and BL finsh dates are not the same i assigned ..............
Regards,
Amir
Dear All,
Plz help
I've a baseline schedule with some actual dates and duatation % complete. but when i assigned the same to updated prgramme the BL start and BL finsh dates are not the same i assigned ..............
Regards,
Amir
Assuming you are using Primavera?
This sounds like the classic issue of planned dates vs actual.
Paul Harris has done an excellent presentation explaining how this works:
http://eastwoodharris.com/DL/TP/110616_P6_V7_What_Baseline_Bars_am_I_Displaying.pdf