Original Duration change equal to Remaining Duration???

X
xadlim B. 👤 Member for 14 years 4 months

 

 Need help please.... Why is it that Original Duration in the Summary Level will change equal to Remaining Durationafter I update some activities??? Due to this reason my Duration % Complete in the Highest or Project Level will always be 0% since Duration % Complete is computed based in the formula D%= (Original Duration (Current Duration) - Remaining Duration / Original Duration (Current Duration) * 100.  Thanx for your input.

Forum Sponsor

Top Posters

anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
Hunais M J
0 posts
Soheil Barekat
4 posts