Remaining units - Primavera

Hi

Looking for some help.

In the schedule I am currently working on , I do not want to record actual units against each activity.

Is there a way in Primavera to make the remaining labour units = estimate to complete labour units?
This would mean as the % complete increases the remaining units automatically decreases.

Hope someone can help

O
Oliver Melling 👤 Member for 19 years 1 month

Hi Roger,

Look up auto-compute actuals in the help...i think this is what you are looking for.

HTH