Hi
Looking for some help.
In the schedule I am currently working on , I do not want to record actual units against each activity.
Is there a way in Primavera to make the remaining labour units = estimate to complete labour units?
This would mean as the % complete increases the remaining units automatically decreases.
Hope someone can help
Hi Roger,
Look up auto-compute actuals in the help...i think this is what you are looking for.
HTH