Search

Technical Specifications for Scheduling

Forum Topic

Anyone have a sample of a detail technical specification for Scheduling, please forward a copy to my email address use private message service  Thank you.   Regards, Marie Albert

Nov 26, 2012

Project Progress Percentage in P6

Forum Topic

I need some assistance about progress percentage in P6. I want to know that how can compare my baseline (Planned) progress and current progres percentage in P6. I understand the concept of three types of individual activity percentages i.e. Physical,...

Nov 26, 2012

Activity codes in P6 for a shopping mall

Forum Topic

Hi, I have recently moved to P6 from MSP and therefore havea only a basic knowledge of P6. I am preparing a schedule for a massive shopping mall (2basements + 4 shopping floors +2 parking floors) and i wanted to know what level of activity codes need...

Nov 5, 2012

Weekly Reports

Forum Topic

Afternoon all, Quick query re reporting in P6..... Is it possible to run a report which shows all the activities that should have been progressed in the previous period but have not been?  I.E Basically at the moment I am filtering the P6 plan to sho...

Nov 5, 2012

"Composite" Timescale in MSP2010

Forum Topic

Hi, Hoping someone can help. I was wondering if MSP 2010 has the capability to show an "composite" timescale on the Gantt charts? By this, I mean something akin to P3 where you can showthe main timescale for the project duration on say a quarterly ba...

Nov 6, 2012

Problem with Import single digit lag from .DBF

Forum Topic

 I got problem in lag when I was importing from .DBF file. I am getting only two digit onwards, but I’m not getting single digit (from 1 to 9) in import. And I tried with decimal (like 3.00) places also and even two digits (like 03). Not able to impo...

Nov 6, 2012

S-Curve

Forum Topic

I made a P6 plan on the basis of manhours now i want to make a S-Curve on excel for manhours weight% vs time for daily progress monitoring. 

Nov 6, 2012

Research Project Management

Forum Topic

I wish to use MS Project to manage my part-time MSc(Res)/PhD course over the next 5-6 years. I've had some basic experience using MS Project for routine IT project management, but it's not obvious how to handle some of the non-standard aspects of a p...

Nov 7, 2012

Baselined dates change when assigned back to the plan

Forum Topic

I have amended some activities on the restored baseline and the dates are all accurate.  When I then assign the baseline back to the main plan a couple of the baseline dates change back/ close to the data date.  This only happens to a couple of activ...

Nov 7, 2012

Planned start & Finish change

Forum Topic

Dear friends, Activity 1 ---FS---- Activity 2 Activity 1 - Start date 25 jul-2012Finish Date 16-aug-2012 Later i clicked the check box for Actual start date - 29-jul-2012 and Actual Finish date as 31-aug-2012 Activity 2 - Planned start is 17aug-2012P...

Nov 8, 2012

P6R7: Sub_Contractor Ressources loading

Forum Topic

Dear P6 experts;I wanna adding some ressources on my P6 project, this ressources is the subcontractor team, so if I add this team as labor, I can't assign a unit of mesure (m3 or lm,..) wich are the units on the subcontractor contract.Please if any o...

Nov 8, 2012

'Straightening the Progress Line'

Forum Topic

Looking for some help: I am trying to ‘straighten the progress line’ in Microsoft Project. I am looking to establish the projected end date of activities and projected end date of the project following the input of progress. I have tried to use the f...

Nov 9, 2012

Planning Schedule Considerations

Forum Topic

Hi Everybody,I am Ashik working as a Project Planner. I wanted to know before starting of the schedule which things i need to considerFor Example : 1. Which Relationship is preferrable for Links (SS or FS or FF) for monitoring?2. Lead or Lag is prefe...

Nov 11, 2012

how to generate a planned vs actual curve basis on duration ?

Forum Topic

I m working with a schedule wich is without cost & loadedmy duration % complete = 12.33 & my schedule % complete = 40% Keeping in view above percentage i would like to show curves on the basis of duration.  thanks in advance 

Nov 12, 2012