I m working with a schedule wich is without cost & loaded
my duration % complete = 12.33 & my schedule % complete = 40% Keeping in view above percentage i would like to show curves on the basis of duration. thanks in advance
I m working with a schedule wich is without cost & loaded
my duration % complete = 12.33 & my schedule % complete = 40% Keeping in view above percentage i would like to show curves on the basis of duration. thanks in advance
thanks.......got it
By definition to draw a curve you need two axis. Typically in planning these axis are time and resource quantity/cost.
if you want to use time for both axis, you need to add a resource that equals the time. When you add a resource to an activity the default quantity is ususally 1h/h..... Therefore you need to add the same resource to every activity in the plan. That means the resource qauntity will equal the duration.
All P6's resource/earned curves will be based on the duration of the activities.