how to generate a planned vs actual curve basis on duration ?

I
Irfan Khan 👤 Member for 16 years 10 months

I m working with a schedule wich is without cost & loaded

my duration % complete = 12.33 & my schedule % complete = 40% Keeping in view above percentage i would like to show curves on the basis of duration.  thanks in advance 

D
David Kelly 👤 Member for 21 years 7 months

By definition to draw a curve you need two axis.  Typically in planning these axis are time and resource quantity/cost.

 

if you want to use time for both axis, you need to add a resource that equals the time.  When you add a resource to an activity the default quantity is ususally 1h/h..... Therefore you need to add the same resource to every activity in the plan.  That means the resource qauntity will equal the duration.

All P6's resource/earned curves will be based on the duration of the activities.

Forum Sponsor

Top Posters

sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
James Williams
74 posts