Dear friends,
Activity 1 ---FS---- Activity 2 Activity 1 - Start date 25 jul-2012Finish Date 16-aug-2012 Later i clicked the check box for Actual start date - 29-jul-2012 and Actual Finish date as 31-aug-2012 Activity 2 - Planned start is 17aug-2012Planned Finish is 21-sep-2012 Actual start is 1-sep-2012Actual finish is 23-oct-2012 Now i scehduled today(08-nov-2012), and added column Planned start & Finish and Actual start & finish. The dates under Actuals are same as i entered. But the dates under Planned start was completely different. And also Activity 1 is not FS relationship with Activity 2. am really confused and dont know what to do. Experts kindly help me. Sivaganesh.S