'Straightening the Progress Line'

Looking for some help:

I am trying to ‘straighten the progress line’ in Microsoft Project.

I am looking to establish the projected end date of activities and projected end date of the project following the input of progress.

I have tried to use the following function but with no result:

Tools > Options > Calculation

  • Updating task status updated resource status
  • Move end of completed parts status date back to status date
  • And remove start of remaining parts back to status date
  • Move start of remaining parts before status date forward to status date
  • And move end of completed parts forward to status dates

Please Help.

 

Gordon.

I
Ismet Kocaman 👤 Member for 16 years 4 months

I hope I did not misunderstand your question. 

Pls make sure the option "Split in-progress tasks" is checked (note that, Project does not split/move fixed-duration type tasks). If you have all the "Move end/And move" options checked (as mentioned in your post), Project aligns the progress with the status date as soon as you input some progress on the tasks. 

Pls also see the following article:

http://office.microsoft.com/en-us/project-help/specify-how-task-progres…

Regards,

Ismet

projectuser[at]fastmail.fm

Featured Partner

Top Posters

Zine Eddine
2 posts
Alex Lyaschenko
27 posts
mxsiegel
0 posts
Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts