Search

RESOURCES LIST

Forum Topic

Hi, Anyone have a copy of all construction trades with task? How about productivity of all trades???   Regards,

Jul 21, 2011

P6 Installation

Forum Topic

Guys' I need some help please! When I installed P6 on my laptop at the first time, everything were installed succesfully including the SQL 2005 server. However when the system is in the process of configuring its databases, PMDB & MMDB, it failed to ...

Jul 21, 2011

Offshore Facilities Operations & Maintenance Schedule

Forum Topic

Dear Members, I am been recently given a job to create a Operations and Maintenance programme for an Offshore facility, which includes Pipeline O & M, Process & Production Platform O & M, Single Point Mooring (SPM) O & M and along with the same its r...

Jul 21, 2011

Showing a resource limit

Forum Topic

I have a plan which is loaded with man hours, however I can only fit a certain number of men on board the vessel so I want to show a limit on the number of hours in any one day.   Can anyone tell me how to set a limit.   I know you can do this on eac...

Jul 21, 2011

Primavera 6.7 Service Pack 3 Hot Fix 2

Forum Topic

Hello, About to the test the Hot Fix 2 for Primavera 6.7 SP3 and was wondering if anyone has experienced any issue since applying this upgrade patch? Thanks,Stuart

Jul 21, 2011

Export/Import multiple P6 projects data to excel

Forum Topic

I need to export resource units data from P6 into excel on up to 200 managed projects, and then need to re-import this modified resource/units data back to P6 v6.1 from Excel, once project managers have updated it.  The import facility available to s...

Jul 21, 2011

MS Project training sessions in Mali

Forum Topic

Are you staying in Western / Central Africa, and looking for a comprehensive training about MS Project, but not willing to travel to Europe for that?Are you unable to get a training in Europe because of visa restrictions?Enroll in the next session or...

Jul 22, 2011

Cost Loading the Schedule

Forum Topic

Hi,I would like to cost load the schedule. I do not want to cost load it based on units/time. I want to give an activity a Lump Sum Budgeted Cost. Get a cost curve to see how much we would be spending per month.I have created a Non-labor Resource cal...

Jul 22, 2011

PERFORMANCE PERCENT COMPLETE ENCOUNTER PROBLEM

Forum Topic

To all co-Planners,I have an unexpeted encounter probs:Facts:I am using P6.1 stand alone.Resource loaded and cost loaded (manpower in 0 price/unit and cost in lump sum 1 price/unit).Using the project as base line.Duration type: Fixed duration and uni...

Jul 23, 2011

Broken Bars in Bar Chart

Forum Topic

Hello All,I have Prepared a schedule in P6 and after making initial schedule and Assigning cost to all activities (No Resource Loading Required for the project,only activity cost from BOQ),I saved the Schedule as Primry Baseline.Now When I update the...

Jul 24, 2011

Multiple Critical Path

Forum Topic

Planners;If the project is devided on two sections,section 1--> finish milestone 1section 2--> finish milestone 2(finish milestone 1) greather than (finish milestone 2)Actualy the TF of FM2 =Finish(FM1)-Finish(FM2)I there any way to show critical pat...

Jul 24, 2011

Re-forecast Vs Re-baseline

Forum Topic

What is the difference between Re-forecast and Re-baseline? What should be the criteria of defining bothterms?

Jul 25, 2011

P 6 Constraints not being honored

Forum Topic

We have a number of projects which are update once a week re scheduled and levelled and for months applied Constraint dates have been honored but in the last few weeks these constriants are not working unless they are Mandatory Constraints.  I suspec...

Jul 25, 2011

independent Activity

Forum Topic

I'm looking for some information as to what an independent activty actually is and how it is used. What I've found to date is some info that relates to software programing but actually feel that it may deal with risk within a project.   I'm open for ...

Jul 25, 2011

actual curve in p3 from tabular report

Forum Topic

 Dears,I have question about generating the actual curve in p3, when i update my schedule to a specific data date and generate resource tabular report i get tow different information regarding the actual quantities for resource loading one for early ...

Jul 25, 2011

Air Max Spam

Forum Topic

Hi Admin Please can you block these spammere lun19890528 lun19890528 liu ling It has just posted about 100 spam messages which I am currently deleting one by one. Can we make it easeir for moderators to block delete such messages - just be searching ...

Jul 26, 2011

Risk Analysis and TIA

Forum Topic

Hello All,It is a humble request to all PP Users that I need to make a report for Risk analysis and Time impact anaylysis (TIA).I shall be grateful is anyone will send me a format or a sample report at  [email protected] or frb_aries@yahoo...

Jul 26, 2011