sample of sequence of work of building construction
Forum Topicplease anyone can help me i need 1 sample project of building construction
please anyone can help me i need 1 sample project of building construction
Dear P6 experts;I wanna adding some ressources on my P6 project, this ressources is the subcontractor team, so if I add this team as labor, I can't assign a unit of mesure (m3 or lm,..) wich are the units on the subcontractor contract.Please if any o...
Looking for some help: I am trying to ‘straighten the progress line’ in Microsoft Project. I am looking to establish the projected end date of activities and projected end date of the project following the input of progress. I have tried to use the f...
Hi Guys,Instantis was acquired by Oracle this week - What does this mean for Primavera? http://ow.ly/fbpgJEmily
Hi Everybody,I am Ashik working as a Project Planner. I wanted to know before starting of the schedule which things i need to considerFor Example : 1. Which Relationship is preferrable for Links (SS or FS or FF) for monitoring?2. Lead or Lag is prefe...
I m working with a schedule wich is without cost & loadedmy duration % complete = 12.33 & my schedule % complete = 40% Keeping in view above percentage i would like to show curves on the basis of duration. thanks in advance
Hi Guys, Here are 5 Reasons Team Members Don’t Deliver On Their Promises http://ow.ly/fdb1l Emily
Hi folksI am having some issues when creating a very selective filter. The information I want to display is very specific but to add salt to injury I can only use one filter and not a combination of them. As you know Reports in P6 only allow to creat...
Most of you may know this, but I just stumbled across it today: there is a 64-bit version of PRA that was issued in September (8.7sp5). No problem installing and it seems to be a little faster - need to test it on a plan with Risk Factors, to be sure...
How can I get the Rolled up Values on the Summary Rows to sum up the Filtered values only. I have run a filter to show Material resourced Tasks only, but the Rolled Up costs show the Sum for all tasks (including the labour ones which are not showing)...
Hi,I am very new to the Microsoft Project 2010. Due to the conditions, I need to use the MS Project 2010 and I have not much idea about it. I have done the baseline program with resources. Now I want to monitor the status for this project. I did set ...
Dear All, Currently I am working in a DG Sewerage project, our task is to calculate the delay for each shaft. My question is that how to link the delayed days with the total float of the BL . Also other than window analysis is there any other method...
I was wondering if it is possible to add a formula to user defined columns similar to how excel formulas work.For example (Column A x Column B) Thanks in advance
Hi to All,I am trying to do on P6 (V7) what I used to do when I was working on P3 a several years ago.I used to generate my S-Curves on Excel from P3 by computing a Tabular Report displayed the following way :TimeEarly startLate StartEarly FinishLate...
I am exploring the way that how to assign weights to my schedule I am using cost & resource loaded schedule Duration Type = Fixed Duration & Units % complete type = Duration Duration % complete = 12.33% Schedule % Complete = 20.35% Performance % Comp...
Hi All, I was importing programme from MS project to P6.It's quite difficult to assign a baseline on the progress programme,because everymonth there will be new activities added to MS project.So when import this to P6 and assigning the baseline to th...
Hi Guys, Here's a new video walk through on using The BI Publisher Reports in Primavera P6 EPPM http://ow.ly/fjeXx I hope you find this useful. Emily
Fellow Planners, I am new to PV so you guys will have to humor me for a bit.Have a question about my finish date in the plan I have just created in PV. If a task gets completed earlier than "finish" date, when I put in the actual (and schedule), the ...
Does anybody uses Critical Chain Project Management .... which software supports this method of scheduling and tracking.
Hi guys,I was hoping someone would be able to assist on this small query of mine. I have been asked to put a programme together for a client of my employer. While reading through the contract, I seen a section that says the programme im putting toget...