How to assign weights to Schedule ?

I
Irfan Khan 👤 Member for 16 years 10 months

I am exploring the way that how to assign weights to my schedule

I am using cost & resource loaded schedule

Duration Type = Fixed Duration & Units

% complete type = Duration

Duration % complete = 12.33%

Schedule % Complete = 20.35%

Performance % Complete = 17.89%

Here I want to know the way of assigning the weights to each activity coz my manager is asking to show me the planned weights & Actual Weights.

Thax in advance…… J

J
Jose Frade 👤 Member for 21 years

Not sure if I got your point because if the Schedule is populated with cost and resources then the weights are already there.

Planned weights can be taken from Base line while Actual weights can be taken from progress made on each period (calendar / finacial / etc)

 

BR

 

JMFrade

Forum Sponsor

Top Posters

sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
James Williams
74 posts