I am exploring the way that how to assign weights to my schedule
I am using cost & resource loaded schedule
Duration Type = Fixed Duration & Units
% complete type = Duration
Duration % complete = 12.33%
Schedule % Complete = 20.35%
Performance % Complete = 17.89%
Here I want to know the way of assigning the weights to each activity coz my manager is asking to show me the planned weights & Actual Weights.
Thax in advance…… J
Not sure if I got your point because if the Schedule is populated with cost and resources then the weights are already there.
Planned weights can be taken from Base line while Actual weights can be taken from progress made on each period (calendar / finacial / etc)
BR
JMFrade