My updates in MSP is not showing the actual start date on Progress bars

Hi,

I am very new to the Microsoft Project 2010. Due to the conditions, I need to use the MS Project 2010 and I have not much idea about it. I have done the baseline program with resources. Now I want to monitor the status for this project. I did set the project as Baseline and start applying actual data to the individual items. Now my progress bars are not starting from the actual start date I am entering in as Actual start. For the items the % progress is more that what actually it should be, but still it doesn't show me early completion date for the items.

I really need your help to sort out this. Please help me.