Calendar Days
Forum TopicI use a 7 days calendar for my project and i would like to see P6 calculates the days by calendar days. But the application is still calculating by working days even my calendar has no non-working days. Please help!
I use a 7 days calendar for my project and i would like to see P6 calculates the days by calendar days. But the application is still calculating by working days even my calendar has no non-working days. Please help!
Is anyone able to assist in the process of being able to export select P6 tasks into a Visio Timeline? Currently I am entering in the tasks and dates manually (and then updating the tasks manually) but was wondering if it was possible to have this do...
Dear All, In Resource usage profile curve how primavera calculates the limit ( Max & min)?
Hi All Please could someone help me . I have set the calender to be 24h ,However if i have a duration of 1 day on the schedule it shows as finishing the following day . E.G if Activity A Duration =1 day , starts 1st April ,the finish date is sh...
Hi All Please could someone help me . I have set the calender to be 24h ,However if i have a duration of 1 day on the schedule it shows as finishing the following day . E.G if Activity A Duration =1 day , starts 1st April ,the finish date is sh...
Hi, I have defined header and footer for a project. The same header and footer reappears for all other projects opned thereafter. Any suggestions to keep separate header and footer for different projects. Thx in advance. Regards, Krish
Hi I have a 78 page schedule and i was wondering if i could create an activity codes table of content with page number.Thanks if you could give me any help on this .I use P6 to create the schedules.
Hi guys i know i started to annoy everybody but sorry its me again and again well lets go for it i have a project and i have lets say 30 workers and i want to divide them in 5 teams every team is 6 workers like this team1 and team2 and team3 and so o...
I need a global to reduce project budgeted manhours by 5% across my project.
On the project I am on, I can only show our Owner specific activities in the schedule as they will not approve a schedule with what my company considers a delay. With this, we escentially have two schedules for our project. Each month we update a sch...
Dear Planners, I have schedule 7000 activities our clints working on with critical activities 850 and longest path only 5 ... why they are not equal or close to geather? Thank you,
Dear Planners, I have schedule 7000 activities our clints working on with critical activities 850 and longest path only 5 ... why they are not equal or close to geather? Thank you,
Hello, I have exported my plan (as a save) and then when i import it back some of the budgeted cost figures are lost or changed. Nobody else has access to the plan. I cannot understand why this is happening, could there be a hidden formula or such th...
Good day all,I have an issue with import from excel to P6.Can I seek any of your expertise is advising me on how to create resource ids particular for a project, assign these to activities in MS excel and them import them in to P6.Cheers,Srinivasan
Dear Expertise of P6. With reference to above mentioned subject i.e. P6 - (Activity % Complete) is not getting summarized as compare to other columns. your valuable inputs are required. Awaiting your usual positive feedback, please consider the snap ...
Is there an add-on for P6 that will create WBS and PERT charts easily such as Critical Tools has built for MS Project.
I am installing stand alone p6 on my laptop. Its 64 bit, AMD laptop.After installing P6 & have following error:Bad public user name or password. Database Server Error: Named Pipes Provider: Could not open a connection to SQL Server [67].Any suggestio...
This is Lesson 2.1 of MS Project Tutorial <<< Lesson here on youtube >>>
Our project is actually delayed and it's due to the client. The client acknowledges the delay (for a lot of reasons), thus agreed to give the contractor a time extension (Time B). However, the developer where the client has a contract with to finish ...
Dear All ,Could you please guide me for main Highway activities or sending me detailed sample for high way schedule Thanks,Amro