Why critical activities not same longets path activities?

J
Jenny Ingco 👤 Member for 14 years 5 months

Dear Planners,

 

I have schedule 7000 activities our clints working on with critical activities 850 and longest path only 5 ... why they are not equal or close to geather?

 

Thank you,

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts