Dear Expertise of P6.
With reference to above mentioned subject i.e. P6 - (Activity % Complete) is not getting summarized as compare to other columns. your valuable inputs are required.
Awaiting your usual positive feedback, please consider the snap shot attached herewith for easy refence.
Thanks in advance.
[[wysiwyg_imageupload:1021:height=311,width=499]]
. Awaiting
Ameen,
you need to configure your performance % complete either you want it to be base on Duration % complete, unit % complete and only performance % complete will show a summary / roll up figures
Ameen,
Suppose, on a project if Design is 20% , Procurement is 10% and Construction is 5%, Would you expect P6 to show you summary % as 35% ? So, There's this logic why P6 doesn't show Activity % at summary level.
To get overall %, you need to define a common variable among multidisciplinary project activities
Cheers,
It is Man Hours loaded and the desired results are coming via Global Change application.
That particular column does not appear to summarize since it is called "Activity % Complete" as opposed to "% complete".
If you want the summary you have to choose the percent complete type that you are using (based on duration, cost etc.). So if you are using durations, you need to select the "Duration % Complete" column and that will summarize based on your durations.
Hi Ameen
Activity % summary can be found on the selected percent complete type you assigned for the project (Duration %, Units %), physical % is a different story
If it is cost loaded, check the performance % and cost % or expense %
3
.