Search

question about contract analysis ?

Forum Topic

Dear planners i need summary for contract anaylsis, like what is contract anaylsis what is the big points that i must looking for it when i analysis a contractplease advise

Jul 1, 2011

How to show planned / as buit / and

Forum Topic

Similar to the last post but i need a step by step guide in the following scenario.   I have inherited a project with an Asta easy plan programme ( I don't usually use Asta) The project is delayed and I want to show the Planned as a baseline that doe...

Jul 1, 2011

Baseline costs showing up incorrectly

Forum Topic

I have a cost loaded baseline schedule that was originally received from the subconstractor is showing a Budgeted Total Cost of $23,835,030. I have received their latest update and the Budgeted Total Cost is $24,613,252. I have assigned the baseline ...

Jul 1, 2011

Trouble with Overtime Rates

Forum Topic

I have a resource eg  rigger working 8 hrs a day(9am to 5pm) for Rs.300/day as standard. I gove him an overtime rate of Rs.90 per hour. Lets say i have an activity which is planned for one day having this rigger as a resource, the planned cost of the...

Jul 2, 2011

Overtime in Primavera P6

Forum Topic

Hi Gentlemen,I hope Everyone is fine there,I need to ask that How to put the overtime for a resource in Primavera P6.I have Searched and In Resource window I have found an Option of Currency & Overtime in details Tab.But I have No concept that How to...

Jul 2, 2011

Overtime Factor for Resources In PRimavera P6

Forum Topic

Hi Gentlemen,I hope Everyone is fine there,I need to ask that How to put the overtime for a resource in Primavera P6.I have Searched and In Resource window I have found an Option of Currency & Overtime in details Tab.But I have No concept that How to...

Jul 3, 2011

Concept Design Development

Forum Topic

Hello everyone,Has any of you come across the need to schedule the development of a concept design for a mayor infraestructure project?If so, I would appreciate your comments regarding the approach and/or methodology used.Regards, Nelson

Jul 3, 2011

Problem in progress override between p3 and p6

Forum Topic

dear planneri faced problem when i make schedule when i choose progress override in p3 i get result, but when i convert the schedule to p6.7 and make schedule with choose progress override i get different result, i don't know why the result different...

Jul 3, 2011

Global Change Summary Task Actual % Complete

Forum Topic

Dear Experts...Summary task % Complete =((Sum of Completed duration of the Baseline Activities Duration)/(Sum of Baseline Activities Duration))*100.I want to Calcualte the Sumaary task % Complete Based on the Baseline Duration, not based on the Actua...

Jul 4, 2011

Claim Digger-incorrect relations lag changes

Forum Topic

Hi, has anybody faced with the incorrect lag changes in claim digger report when you compare 2 schedules. For example, even the lag is not changed in both schedules, claim digger report is shown as it is changed. And it makes it in lots of activities...

Jul 5, 2011

How to change the data from user defined field to activity code

Forum Topic

Dear All, I want to change a data form user defined field to activity code.  I am not able to group resources in the resource assignment layout  wrt equipment no,since i have assigned it in the user defined field. so now i have to change all the equi...

Jul 5, 2011

Copying relationships for identical activities

Forum Topic

Hello everybody,My issue is I'm having a plan for a 51 residental buildings project, in a stage of construction there will be a lot of similar activities, so I create the activities in one building then I copy them to the other buildings , now I want...

Jul 5, 2011

P6 milestones against progress line

Forum Topic

On my milestones, my P6 progress line completely ignores progress on the milestones (0% or 100%) (ahead or behind) . Progress reporting on the Bars is fine, and the progress line is a good "zig-zag" drop-line. Is there a way of having the progress of...

Jul 5, 2011

Critical Path Quiz answers

Forum Topic

So here are the answers to the quiz, along with an explanation of how to compute critical path drag in a simple (all FS) network:Which activity or activities has/have the most total float, and how much? J has TF = 40Which activity or activities has/h...

Jul 5, 2011

Claim Digger

Forum Topic

Can anybody tell me how to use claim digger in P6. I am having the Icon in P6 window,but when i click it nothing is coming. Kindly help.

Jul 5, 2011

Remain Finish Date vs Remain Start Date.

Forum Topic

Hi everyone, I am using Primavera PM6 to manage the coming workload of our team. We have about 95 projects in progress with 4 to 9 activities in each project. My problem occurs when I open many projects at the same time, the remaining units of some t...

Jul 5, 2011

Just getting started with TILOS

Forum Topic

Im just delving into TILOS for the first time as a new planner. I emailed Tilos support for any reference materials or possibly any trainers in the vecinity of Salt Lake City Utah, but have not recieved any response.Im really  intersted in getting th...

Jul 5, 2011

Trouble Exporting MSProject 2007 files to Primavera Contractor

Forum Topic

I am having huge problems trying to export a project created in MS Project (by my owner) into Primavera's P4 Contractor.I need help so that I don't have to recreate the entire project from scratch. Anyone know a way or a file conversion utility to ac...

Jul 5, 2011

Working Dates Back in Project 2003

Forum Topic

This may be a basic question, but I want to design a plan that works back from a given delivery date. I've discovered I can enter predecessors with a minus number of days, but it doesn't appear to work the dates back consistently. Ideas?

Jul 6, 2011