dear planner
i faced problem when i make schedule when i choose progress override in p3 i get result, but when i convert the schedule to p6.7 and make schedule with choose progress override i get different result, i don't know why the result different? and how can imake it the same ??
please advice
Thank you for your reply, I check the calendar in P3 and P6 it was the same. any other idea
Most of the problems arise from p3 to p6 conversion are calendars problems.
So check that calendars and working hours match those in p3
Hmmm...now you're confused about the whole idea
When I said you should change the sequence yourself, I did not mean that you should change the sequence in favor of the Employer's risk. You should be able to differentiate between your delays and the Employer's ones.
And sometimes there is no delay involved. It is just a change in sequence than that was originally planned.
but also it's not good idea change sequence of work every update, because it will effect in our rights to prepare claim in the furture
Jihad,
Its not a good idea/practice to use progress override to overcome out of sequence activities. You should change the sequence yourself.
Regards,
Haitham.
What happens when you schedule both using retained logic?
When you get different results, what different results do you get?
do these affect completed activities, in progress, or planned?
can you see any pattern with affected activity types, calendars, constraints, resources or relationships?
Do you have out of sequence working?
any one can help me in this problem ????????????