Search

SCHEDULE % NOT MATCHING WITH PERFORMANCE %

Forum Topic

Dear All, Please Help about, on my running schedule, i make revision (extend dates) and copy same schedule as Baseline, But Schedule % not matching with Performance %, even same schedule attched as Baseline.

Oct 1, 2013

Generate S-curve in P6 R8.2

Forum Topic

Dear colleagues,Just want to know, in P6 R8.2, how to generate s-curves for the following:     1. Cost (Plan vs. Actual)     2. Earned Value     3. Schedule Variance     4. Resource LoadingRegards,Leonard

Oct 1, 2013

Duration error - I entered days & it took it as hours.

Forum Topic

I am new to P6 using P6v7.I entered activities & their durations the normal way & added resources to the activities. It is showing like this: -Original Duration Column as 20d [ fine as I entered 20 ]Budgeted Units as 20h in Bottom Layout - Resources ...

Oct 1, 2013

Delay Analysis

Forum Topic

I am trying to calculate delay to a project - there is nothing contractually written that states anything to do with extensions of time within the contract, however, the client and contractor both agreed to re-baseline the schedule when delay started...

Oct 1, 2013

Cumulative Schedule %

Forum Topic

Dear All,Can any one help me. I dont want schedule % complete for some WBS i dont want them to be added in the cumulative %?Any help will be appreciatedThanks

Nov 8, 2013

User defined fields?

Forum Topic

Hi all I have a spreadsheet, with milestone dates on that the boss wants putting into Powerproject.  Theres several headings such as "name", "Value", Status" as well as the dates. Im trying to make my own user defined fields for the headings.  I have...

Nov 8, 2013

Problems change effect

Forum Topic

Dear All, I have imported a schedule from P3 to P6, all seem to be working fine untill I tried to update actuals. the schedule early finish and early end dates seem the same. no effect on succesor activies . how can i over come this problem 

Nov 8, 2013

Resources leveling tool

Forum Topic

Dear all,Does anyone know a tool for leveling schedules that is more efficient than P6 ?Thanks

Nov 8, 2013

Not able to delete or copy a project in P-6-Rel 8.2

Forum Topic

 Dear All, I am having a strange problem, which I never face while using Rel-6.0,6.2,7.0, and that is while deleting/or copying  a program, It states a error code-TINAT-2680-D, or mentioning there is not enough space in database. Please any one advis...

Nov 10, 2013

Diagrams and table reports

Forum Topic

Dear all,I am playing with diagrams and table reports now and have a couple of questions. Just checking, that that I understand the things correctly and not missing something:Both diagrams and table reports are possible to save as a template for futu...

Nov 10, 2013

Multiple WBS

Forum Topic

I have to develop a schedule in P6 8.3 that integrates separate schedules from different Subcontractors.  Since some of the financial information from the Subcontractors’ schedules is confidential, I intend to create separate schedules under a single...

Nov 11, 2013

Display total float on Project level

Forum Topic

Dear Primavera Experts, My question is, How can I display the total float on the Project summary level?The project completion milestone delayed 68 days (TF=-68), But on the project level it shown (TF=0), how can I display on this level the same TF wh...

Nov 11, 2013

How to install P6 version 8.3 stand alone?

Forum Topic

I'm trying to install Primavera P6 V8.3 standalone on a notebook with windows 8 but I can't make it work. I would like to install it with SQL, if possible. Does anyone have some tutorial or some tips? Thanks!

Nov 12, 2013

Cost Account Name - Show in Resources

Forum Topic

Is there a way to show the cost account name along with the cost account ID when it is used in the resource section of an activity?  One does not have the option of adding the name column.Thank you.

Nov 12, 2013

Remaining early start

Forum Topic

Hi everyone,I have an activity that was completed earlier than planned (nov 1st instead of nov 8)Meanwhile its successor remaining early start date remains on november 11th. (the data date is nov 1st)Is there a way to advance the rem. early start to ...

Nov 12, 2013